Amendment C084 (Melton)
WatchThe amendment proposes to: Incorporate the Toolern Precinct Structure Plan (Including the Toolern Native Vegetation Precinct Plan) and Toolern Development Contributions Plan into the Scheme. Update the schedule to Clause 81.01 to reflect the incorporation of the three plans. Introduce Schedule 3 (Toolern Precinct Structure Plan) to the Urban Growth Zone (UGZ) to make the Toolern Precinct Structure Plan the primary land use and development document to guide planning in the area. Introduce Schedule 3 (Toolern Development Contributions Plan) to land within the Toolern Precinct Structure Plan (PSP) area to provide for developer contributions to specific new development and community infrastructure. Make changes to the Local Planning Policy Framework at Clauses 21.03 Planning Visions and Objectives for Melton 21.04 Planning Strategies and Implementation for the Shire 22.01 Residential Land Use Policy 22.05 Employment Policy to update in light of the Toolern Precinct Structure Plan. Provide for public open space contributions for land (excluding employment land) in the Toolern Precinct Structure Plan area when land is subdivided by amending the Schedule to Clause 52.01 to require 9.16% of land or cash payment for Public Open Space. Use the Toolern Native Vegetation Precinct Plan to manage native vegetation in the Toolern Precinct Structure Plan area by listing it in the schedule to Clause 52.16. Delete the Wildfire Management Overlay (WMO) where this applies to land within the PSP area. The removal of the WMO from land within the PSP area is considered appropriate given the rezoning of the land to the UGZ for urban development. The future subdivision of the land for residential purposes will require fire hydrants to be provided in accordance with Clause 56.09-3. Delete Schedule 2 to the Development Plan Overlay (DPO2). Update the schedule to Clause 61.03 to reflect the planning scheme map changes.
- Status date
- 23 Feb 2023
- Exhibition
- ·
- Gazettal
- ·
- Outcome
- SplitParent
Melton
Council profile →- Amendments tracked
- 176
- Last 12 months
- 4
- Approval rate
- 94%
Stage history
-
Withdrawn
source label: “Finished:SplitParent”
Status date 23 Feb 2023 · Observed 12 June 2026 → current
More in MELTON
- Amendment C232melt (Melton) Approved / gazetted· 7 May 2026
- Amendment C231melt (Melton) Approved / gazetted· 15 Oct 2025
- Amendment C243melt (Melton) Approved / gazetted· 15 Oct 2025
- Amendment C246melt (Melton) Approved / gazetted· 18 June 2025
- Amendment C242melt (Melton) Approved / gazetted· 1 May 2024
- Amendment C240melt (Melton) Approved / gazetted· 7 Mar 2024
Planning disputes in Melton
Tribunal and court decisions naming this council, newest first. A signal of contested development in the area, not legal advice.
- Galea v Melton CC [2025] VCAT 880 VCAT· 7 Oct 2025· Galea v Melton CC [2025] VCAT 880
- Scotts Securities Pty Ltd v Melton CC [2024] VCAT 1222 VCAT· 24 Dec 2024· Scotts Securities Pty Ltd v Melton CC [2024] VCAT 1222 Costs
- Mierafe Kidusan Abune Tekele Haymanot Ethiopian Orthodox Tewahedo Church Melbourne Incorporated v Melton CC [2024] VCAT 915 VCAT· 25 Sept 2024· Mierafe Kidusan Abune Tekele Haymanot Ethiopian Orthodox Tewahedo Church Melbourne Incorporated v Melton CC [2024] VCAT 915
- SGL v Melton CC [2024] VCAT 894 VCAT· 19 Sept 2024· SGL v Melton CC [2024] VCAT 894
- Scotts Securities Pty Ltd v Melton CC [2024] VCAT 878 VCAT· 13 Sept 2024· Scotts Securities Pty Ltd v Melton CC [2024] VCAT 878
- Waveconn Operations Pty Ltd v Melton CC [2024] VCAT 567 VCAT· 18 June 2024· Waveconn Operations Pty Ltd v Melton CC [2024] VCAT 567