How long does rezoning take in Merri-Bek?
Every figure below is computed from the official register records for this council. Counts and gazettal years come from full register history; pipeline duration only from what we have directly observed.
- Amendments tracked
- 14
- full register history
- Active last 12 months
- 6
- by latest status date
- Approval rate
- 92%
- of 12 recorded outcomes
- Observed pipeline duration
- —
- insufficient data yet (0 of 5 cases observed)
Gazetted per year
From gazettal dates in the register: full history, not observation-window data.
| Year | Gazetted |
|---|---|
| 2026 | 1 |
| 2025 | 4 |
| 2023 | 6 |
Recent amendments
| Amendment | Stage | Status date | Gazettal | Outcome |
|---|---|---|---|---|
| Amendment C236mbek (Merri-bek) | On exhibition | 10 May 2026 | · | · |
| Amendment C235mbek (Merri-bek) | Assessment | 2 Apr 2026 | · | · |
| Amendment C196more (Merri-bek) | Approved / gazetted | 1 Apr 2026 | 1 Apr 2026 | ApprovedWithChanges |
| Amendment C231mbek (Merri-bek) | Approved / gazetted | 21 Dec 2025 | 21 Dec 2025 | ApprovedWithChanges |
| Amendment C234mbek (Merri-bek) | Approved / gazetted | 13 Aug 2025 | 13 Aug 2025 | Approved |
| Amendment C226more (Merri-bek) | Approved / gazetted | 2 July 2025 | 2 July 2025 | Approved |
| Amendment C232mbek (Merri-bek) | Approved / gazetted | 2 Apr 2025 | 2 Apr 2025 | Approved |
| Amendment C190more (Merri-bek) | Lapsed | 19 Dec 2024 | · | Lapsed |
| Amendment C219more (Merri-bek) | Approved / gazetted | 18 Oct 2023 | 18 Oct 2023 | Approved |
| Amendment C208more (Merri-bek) | Approved / gazetted | 3 Aug 2023 | 3 Aug 2023 | ApprovedWithChanges |
| Amendment C221more (Merri-bek) | Approved / gazetted | 23 June 2023 | 23 June 2023 | ApprovedWithChanges |
| Amendment C225more (Merri-bek) | Approved / gazetted | 2 June 2023 | 2 June 2023 | Approved |
| Amendment C201more (Merri-bek) | Approved / gazetted | 2 June 2023 | 2 June 2023 | ApprovedWithChanges |
| Amendment C218more (Merri-bek) | Approved / gazetted | 24 May 2023 | 24 May 2023 | Approved |
How these numbers are computed
- Volume and gazettals per year count register records directly, full history from the source register.
- Approval rate is recorded outcomes beginning “Approved” over all recorded outcomes. Cases still in flight have no outcome and are excluded.
- Observed pipeline duration is the median days between our first and last stage observation for cases we watched move into approved/gazetted: an observed duration accruing since 12 June 2026, not lodgement-to-gazettal elapsed time, which the registers' list data cannot support. Medians are suppressed below 5 observed cases rather than reported on thin samples.