How long does rezoning take in Knox?
Every figure below is computed from the official register records for this council. Counts and gazettal years come from full register history; pipeline duration only from what we have directly observed.
- Active last 12 months
- 3
- by latest status date
- Approval rate
- 95%
- of 154 recorded outcomes
- Observed pipeline duration
- —
- still building (1 of 5 cases observed)
Gazetted per year
From gazettal dates in the register: full history, not observation-window data.
| Year | Gazetted |
|---|---|
| 2026 | 2 |
| 2025 | 6 |
| 2024 | 3 |
| 2023 | 3 |
| 2022 | 1 |
| 2021 | 1 |
| 2020 | 3 |
| 2019 | 8 |
| 2018 | 4 |
| 2017 | 6 |
Recent amendments
| Amendment | Stage | Status date | Gazettal | Outcome |
|---|---|---|---|---|
| Amendment C196knox (Knox) | Assessment | 15 Oct 2026 | · | · |
| Amendment C194knox (Knox) | Approved / gazetted | 18 June 2026 | 18 June 2026 | Approved |
| Amendment C201knox (Knox) | Approved / gazetted | 4 Feb 2026 | 4 Feb 2026 | Approved |
| Amendment C190knox (Knox) | Approved / gazetted | 20 Oct 2025 | 20 Oct 2025 | Approved |
| Amendment C184knox (Knox) | Approved / gazetted | 15 Oct 2025 | 15 Oct 2025 | ApprovedWithChanges |
| Amendment C202knox (Knox) | Approved / gazetted | 13 Aug 2025 | 13 Aug 2025 | Approved |
| Amendment C192knox (Knox) | Approved / gazetted | 18 June 2025 | 18 June 2025 | Approved |
| Amendment C191knox (Knox) | Approved / gazetted | 28 May 2025 | 28 May 2025 | Approved |
| Amendment C203knox (Knox) | Approved / gazetted | 2 Apr 2025 | 2 Apr 2025 | Approved |
| Amendment C185knox (Knox) | Approved / gazetted | 27 Nov 2024 | 27 Nov 2024 | Approved |
| Amendment C165knox (Knox) | Approved / gazetted | 1 Feb 2024 | 1 Feb 2024 | Approved |
| Amendment C180knox (Knox) | Approved / gazetted | 1 Feb 2024 | 1 Feb 2024 | Approved |
| Amendment C189knox (Knox) | Approved / gazetted | 29 Nov 2023 | 29 Nov 2023 | ApprovedWithChanges |
| Amendment C200knox (Knox) | Approved / gazetted | 23 June 2023 | 23 June 2023 | Approved |
| Amendment C174knox (Knox) | Approved / gazetted | 3 May 2023 | 3 May 2023 | Approved |
| Amendment C193knox (Knox) | Approved / gazetted | 25 Feb 2022 | 25 Feb 2022 | ApprovedWithChanges |
| Amendment C187knox (Knox) | Approved / gazetted | 3 Mar 2021 | 3 Mar 2021 | Approved |
| Amendment C158 (Knox) | Approved / gazetted | 12 Oct 2020 | 12 Oct 2020 | Approved |
| Amendment C176knox (Knox) | Approved / gazetted | 19 Mar 2020 | 19 Mar 2020 | ApprovedWithChanges |
| Amendment C179knox (Knox) | Approved / gazetted | 25 Feb 2020 | 25 Feb 2020 | Approved |
| Amendment C183knox (Knox) | Approved / gazetted | 16 Dec 2019 | 16 Dec 2019 | Approved |
| Amendment C182knox (Knox) | Approved / gazetted | 10 Oct 2019 | 10 Oct 2019 | Approved |
| Amendment C173knox (Knox) | Approved / gazetted | 29 Aug 2019 | 29 Aug 2019 | Approved |
| Amendment C164 (Knox) | Approved / gazetted | 24 July 2019 | 24 July 2019 | ApprovedWithChanges |
| Amendment C160 (Knox) | Approved / gazetted | 24 July 2019 | 24 July 2019 | Approved |
Planning disputes
Planning and environment court and tribunal matters naming Knox. Sort any column, filter by keyword, and click a matter to open the full public judgment. Decisions from the last 12 months.
Showing 1–6 of 6
| Catchwords | |||
|---|---|---|---|
| Zhang v Knox CC [2026] VCAT 826 | VCAT | 7 Oct 2026 | |
| Media Circus (VIC) Pty Ltd v Knox CC [2026] VCAT 534 | VCAT | 8 July 2026 | VIC |
| Ferntree Building Pty Ltd v Knox CC [2026] VCAT 399 | VCAT | 1 June 2026 | |
| Media Circus (VIC) Pty Ltd v Knox CC [2025] VCAT 1129 | VCAT | 29 Dec 2025 | VIC |
| Maple Media Pty Ltd v Knox CC [2025] VCAT 1077 | VCAT | 5 Dec 2025 | |
| Faith Box Hill Pty Ltd v Knox CC [2025] VCAT 953 | VCAT | 29 Oct 2025 |
Discovery signals matched on council name. We link to the public judgment; we do not reproduce its text.
How these numbers are computed
- Volume and gazettals per year count register records directly, full history from the source register.
- Approval rate is recorded outcomes beginning “Approved” over all recorded outcomes. Cases still in flight have no outcome and are excluded.
- Observed pipeline duration is the median days between our first and last stage observation for cases we watched move into approved/gazetted: an observed duration accruing since 12 June 2026, not lodgement-to-gazettal elapsed time, which the registers' list data cannot support. Medians are suppressed below 5 observed cases rather than reported on thin samples.