How long does rezoning take in Casey?
Every figure below is computed from the official register records for this council. Counts and gazettal years come from full register history; pipeline duration only from what we have directly observed.
- Active last 12 months
- 7
- by latest status date
- Approval rate
- 88%
- of 294 recorded outcomes
- Observed pipeline duration
- —
- still building (2 of 5 cases observed)
Gazetted per year
From gazettal dates in the register: full history, not observation-window data.
| Year | Gazetted |
|---|---|
| 2026 | 5 |
| 2025 | 5 |
| 2024 | 5 |
| 2023 | 6 |
| 2022 | 6 |
| 2021 | 10 |
| 2020 | 8 |
| 2019 | 19 |
| 2018 | 1 |
| 2017 | 5 |
Recent amendments
| Amendment | Stage | Status date | Gazettal | Outcome |
|---|---|---|---|---|
| Amendment C302case (Casey) | Approved / gazetted | 23 Sept 2026 | 23 Sept 2026 | ApprovedWithChanges |
| Amendment C304case (Casey) | Approved / gazetted | 13 Aug 2026 | 13 Aug 2026 | Approved |
| Amendment C300case (Casey) | Assessment | 3 July 2026 | · | · |
| Amendment C296case (Casey) | Approved / gazetted | 18 June 2026 | 18 June 2026 | Approved |
| Amendment C291case (Casey) | Approved / gazetted | 1 Apr 2026 | 1 Apr 2026 | ApprovedWithChanges |
| Amendment C303case (Casey) | Approved / gazetted | 1 Apr 2026 | 1 Apr 2026 | Approved |
| Amendment C286case (Casey) | Approved / gazetted | 21 Dec 2025 | 21 Dec 2025 | ApprovedWithChanges |
| Amendment C284case (Casey) | Approved / gazetted | 15 Oct 2025 | 15 Oct 2025 | ApprovedWithChanges |
| Amendment GC238 (Casey) | Approved / gazetted | 15 Oct 2025 | 15 Oct 2025 | Approved |
| Amendment GC237 (Casey) | Approved / gazetted | 13 Aug 2025 | 13 Aug 2025 | Approved |
| Amendment C301case (Casey) | Approved / gazetted | 18 June 2025 | 18 June 2025 | Approved |
| Amendment C275case (Casey) | Approved / gazetted | 20 Mar 2024 | 20 Mar 2024 | ApprovedWithChanges |
| Amendment C207 (Casey) | Withdrawn | 12 Mar 2024 | · | SplitParent |
| Amendment C288case (Casey) | Approved / gazetted | 7 Mar 2024 | 7 Mar 2024 | ApprovedWithChanges |
| Amendment C253case (Casey) | Approved / gazetted | 5 Feb 2024 | 5 Feb 2024 | Approved |
| Amendment C259case (Casey) | Approved / gazetted | 1 Feb 2024 | 1 Feb 2024 | Approved |
| Amendment C281case (Casey) | Approved / gazetted | 1 Feb 2024 | 1 Feb 2024 | Approved |
| Amendment C293case (Casey) | Approved / gazetted | 18 Oct 2023 | 18 Oct 2023 | Approved |
| Amendment C292case (Casey) | Approved / gazetted | 23 June 2023 | 23 June 2023 | Approved |
| Amendment GC181 (Casey) | Approved / gazetted | 22 May 2023 | 22 May 2023 | Approved |
| Amendment C287case (Casey) | Approved / gazetted | 3 May 2023 | 3 May 2023 | Approved |
| Amendment C290case (Casey) | Approved / gazetted | 21 Mar 2023 | 21 Mar 2023 | Approved |
| Amendment C273case (Casey) | Approved / gazetted | 8 Feb 2023 | 8 Feb 2023 | Approved |
| Amendment GC150 (Casey) | Approved / gazetted | 7 Sept 2022 | 7 Sept 2022 | ApprovedWithChanges |
| Amendment C207pt1case (Casey) | Approved / gazetted | 6 Sept 2022 | 6 Sept 2022 | ApprovedWithChanges |
Planning disputes
Planning and environment court and tribunal matters naming Casey. Sort any column, filter by keyword, and click a matter to open the full public judgment. Decisions from the last 12 months.
Showing 1–5 of 5
| Catchwords | |||
|---|---|---|---|
| JY Haben No.2 Pty Ltd v Casey CC [2026] VCAT 603 | VCAT | 31 July 2026 | |
| Dasler v Casey CC [2026] VCAT 366 | VCAT | 20 May 2026 | |
| Maple Media Pty Ltd v Casey CC [2026] VCAT 71 | VCAT | 6 Feb 2026 | |
| Taylor v Casey CC [2026] VCAT 10 | VCAT | 8 Jan 2026 | |
| Dragic v Casey CC [2025] VCAT 1084 | VCAT | 9 Dec 2025 |
Discovery signals matched on council name. We link to the public judgment; we do not reproduce its text.
How these numbers are computed
- Volume and gazettals per year count register records directly, full history from the source register.
- Approval rate is recorded outcomes beginning “Approved” over all recorded outcomes. Cases still in flight have no outcome and are excluded.
- Observed pipeline duration is the median days between our first and last stage observation for cases we watched move into approved/gazetted: an observed duration accruing since 12 June 2026, not lodgement-to-gazettal elapsed time, which the registers' list data cannot support. Medians are suppressed below 5 observed cases rather than reported on thin samples.