Amendment C292case (Casey)
WatchThe amendment extends the expiry date of interim heritage controls in the Cranbourne Major Activity Centre in Cranbourne and Cranbourne East until 30 November 2023.
- Status date
- 23 June 2023
- Exhibition
- ·
- Gazettal
- 23 June 2023
- Outcome
- Approved
Stage history
-
Approved / gazetted
source label: “Finished:Approved”
Status date 23 June 2023 · Observed 12 June 2026 → current