How long does rezoning take in Campaspe?
Every figure below is computed from the official register records for this council. Counts and gazettal years come from full register history; pipeline duration only from what we have directly observed.
- Amendments tracked
- 122
- full register history
- Active last 12 months
- 2
- by latest status date
- Approval rate
- 92%
- of 122 recorded outcomes
- Observed pipeline duration
- —
- insufficient data yet (0 of 5 cases observed)
Gazetted per year
From gazettal dates in the register: full history, not observation-window data.
| Year | Gazetted |
|---|---|
| 2025 | 4 |
| 2024 | 4 |
| 2023 | 3 |
| 2022 | 2 |
| 2020 | 3 |
| 2019 | 2 |
| 2017 | 2 |
| 2016 | 3 |
| 2015 | 1 |
| 2014 | 5 |
Recent amendments
| Amendment | Stage | Status date | Gazettal | Outcome |
|---|---|---|---|---|
| Amendment C127camp (Campaspe) | Approved / gazetted | 15 Nov 2025 | 15 Nov 2025 | Approved |
| Amendment GC196 (Campaspe) | Approved / gazetted | 20 Oct 2025 | 20 Oct 2025 | Approved |
| Amendment C122camp (Campaspe) | Approved / gazetted | 2 Apr 2025 | 2 Apr 2025 | Approved |
| Amendment C125camp (Campaspe) | Approved / gazetted | 19 Feb 2025 | 19 Feb 2025 | Approved |
| Amendment C126camp (Campaspe) | Approved / gazetted | 27 Nov 2024 | 27 Nov 2024 | Approved |
| Amendment C124camp (Campaspe) | Approved / gazetted | 1 May 2024 | 1 May 2024 | Approved |
| Amendment C120camp (Campaspe) | Approved / gazetted | 7 Mar 2024 | 7 Mar 2024 | Approved |
| Amendment GC173 (Campaspe) | Approved / gazetted | 31 Jan 2024 | 31 Jan 2024 | Approved |
| Amendment C103 (Campaspe) | Approved / gazetted | 8 Sept 2023 | 8 Sept 2023 | Approved |
| Amendment C118camp (Campaspe) | Approved / gazetted | 7 June 2023 | 7 June 2023 | ApprovedWithChanges |
| Amendment C117camp (Campaspe) | Approved / gazetted | 22 Mar 2023 | 22 Mar 2023 | ApprovedWithChanges |
| Amendment C121camp (Campaspe) | Approved / gazetted | 27 Oct 2022 | 27 Oct 2022 | Approved |
| Amendment GC151 (Campaspe) | Approved / gazetted | 11 Feb 2022 | 11 Feb 2022 | Approved |
| Amendment C111camp (Campaspe) | Approved / gazetted | 15 Dec 2020 | 15 Dec 2020 | ApprovedWithChanges |
| Amendment GC160 (Campaspe) | Approved / gazetted | 30 June 2020 | 30 June 2020 | Approved |
| Amendment C116camp (Campaspe) | Approved / gazetted | 19 Mar 2020 | 19 Mar 2020 | Approved |
| Amendment C110 (Campaspe) | Approved / gazetted | 24 July 2019 | 24 July 2019 | ApprovedWithChanges |
| Amendment C112camp (Campaspe) | Approved / gazetted | 4 July 2019 | 4 July 2019 | Approved |
| Amendment C104 (Campaspe) | Approved / gazetted | 21 Dec 2017 | 21 Dec 2017 | ApprovedWithChanges |
| Amendment C082 (Campaspe) | Withdrawn | 28 June 2017 | · | SplitParent |
| Amendment C109 (Campaspe) | Approved / gazetted | 9 Mar 2017 | 9 Mar 2017 | Approved |
| Amendment C105 (Campaspe) | Approved / gazetted | 10 Nov 2016 | 10 Nov 2016 | ApprovedWithChanges |
| Amendment C101 (Campaspe) | Approved / gazetted | 21 July 2016 | 21 July 2016 | ApprovedWithChanges |
| Amendment C106 (Campaspe) | Approved / gazetted | 26 May 2016 | 26 May 2016 | Approved |
| Amendment GC35 (Campaspe) | Approved / gazetted | 19 Nov 2015 | 19 Nov 2015 | Approved |
Planning disputes
16 on recordPlanning and environment court and tribunal matters naming Campaspe, newest first. Each links to the full public judgment.
| Matter | Court | Decided |
|---|---|---|
| Johnston v Campaspe SC [2025] VCAT 816 | VCAT | 16 Sept 2024 |
| Touhey v Campaspe SC [2023] VCAT 1142 | VCAT | 1 Nov 2023 |
| Hume v Campaspe SC [2023] VCAT 1109 Costs | VCAT | 26 Sept 2023 |
| Daldy v Campaspe SC [2023] VCAT 1052 | VCAT | 14 Sept 2023 |
| Prosser v Campaspe SC [2023] VCAT 1038 | VCAT | 7 Sept 2023 |
| Pearce v Campaspe SC [2023] VCAT 983 | VCAT | 24 Aug 2023 |
| Cinanni v Campaspe SC [2023] VCAT 797 | VCAT | 13 July 2023 |
| Touhey v Campaspe SC [2023] VCAT 709 | VCAT | 23 June 2023 |
| Prosser v Campaspe SC [2023] VCAT 310 | VCAT | 27 Mar 2023 |
| Hume v Campaspe SC [2023] VCAT 288 | VCAT | 20 Mar 2023 |
| Grange Pastures Pty Ltd v Campaspe SC [2022] VCAT 1480 | VCAT | 22 Dec 2022 |
| Albert v Campaspe SC [2022] VCAT 767 | VCAT | 6 July 2022 |
| Warren v Campaspe SC [2022] VCAT 464 Corrected | VCAT | 7 June 2022 |
| Wiltshire v Campaspe SC [2022] VCAT 549 | VCAT | 16 May 2022 |
| Biddle v Campaspe SC [2021] VCAT 1493 | VCAT | 22 Dec 2021 |
| Iannacone v Campaspe SC [2021] VCAT 838 | VCAT | 28 July 2021 |
Discovery signals matched on council name. We link to the public judgment; we do not reproduce its text.
How these numbers are computed
- Volume and gazettals per year count register records directly, full history from the source register.
- Approval rate is recorded outcomes beginning “Approved” over all recorded outcomes. Cases still in flight have no outcome and are excluded.
- Observed pipeline duration is the median days between our first and last stage observation for cases we watched move into approved/gazetted: an observed duration accruing since 12 June 2026, not lodgement-to-gazettal elapsed time, which the registers' list data cannot support. Medians are suppressed below 5 observed cases rather than reported on thin samples.